ONly about Material Management

SAP MM FAQ


SAP Material Management Frequently Asked Question


Q: How can I extend all material to a new plant?

A: The SAP program - RMDATIND is used to create /update material master record.


Q: How can we delete materials permanently from Material master?

A: Use transaction MM70 - Material Master->Other->Reorganization->Material->Choose.

Build variant with selection range of material master records to be selected for

Deletion and maintain,
Run parameters.

Execute.

Use transaction MM71 - Material Master-> other-> Reorganizationn-->Material->Reorganization

Build a second variant Maintain run parameters and execute.

It is also important to remove the records manually from info record, POs, PRs, reservation etc For successful deletion of the material.


Q: SAP only provides moving average value for current, previous period, and previous year. SAP does not provide transactions/reports that will provide moving average value for a given date.

How can I report moving average price for material number 10000000 at plant 0001 on July 4,1998 ?

A: Try any of these solutions:

1. Change the updating level of the structure (S031) to "daily". In LIS the total value and the total stock are available. Divide value by the stock. It is possible to calculate this dynamically when the analysis is run and to display the result.

2. Create your own structure in LIS and populate it by copying the Moving Average Price from the material master every time there is a transaction. You will have data on those days when there was a transaction.


Q: We have defined all the variables for the materials. However, when I attempt to use Material Matchcode object MAT1, I get the response "No possible entries found". Why?

A: Matchcode i.d. "B", "Material by bill of material" has a selection condition for field STLNR NE ' '. STLNR is the BOM number associated with a material in table MAST. Hence the message - "no possible entries..." pops up if there are no bills of materials associated with your material numbers.

You get the matchcodes as long as the material referred by you has BOM number associated with it.


Q: The matchcode object selection is defaulted to matctcode ID "B". Iwould like to change to M " Material by Description" What is the solution?

A: Press the pull down arrow on the material number field and matchcode "B" is displayed, press F5 double-click matchcode i.d. "M", then press F6 . This will set matchcode "M" as the default.


Q: We have one material master : X and the unit of measure is 'pcs' and two serial number : A,B For this material we make two Pos
First PO calls material X , 1 pcs price 100 (will use serial number A)
Second PO calls material X , 1 pcs price 250 (will use serial number B)
Goods Receipt is done and by filling serial number for the fist PO with A and the second PO with B. We want to transfer material X serial number A to another plant and want the valuation of this material as 100. How we can do it ?


A: Use "split valuation". Stocks may be received into separate storage locations. Transfer stocks may be done from a storage location/plant to another storage location/plant.

Q: We want to change the calculation of Moving Average Price. We know that the same is in MBEW-VERPR and two transactions to consider - MRHR, MB01. Is there a transaction to change MAV or all the places it is needed?


A: Any Goods receipt or issue (in case of split valuated material) changes Moving Average price depending upon the valuation type which is used when posting the goods issue. You have t go through all the transactions involving those!

For Example:

Material X is using split valuation by origin:
Malaysia : MAV 60 USD - total stock 100 units
India: MAV 50 USD - total stock 200 units
Total stock 300 units MAV 53.33

Here , goods issues will also affect the global MAV, despite not changing MAV from origin country.


Q: What is the use of configurable material.?

A: Configurable material is useful if you have a large number of combination of parts that go into a product. It means different permutations and combinations of the parts for same material. If you maintain a unique material code for each combination , you require a large number of material numbers. KMAT may be used in such a case where you maintain just one generic product code.

A super BOM is maintained for such a material consisting of all possible alternatives. A routing is also maintained consisting of all possible operations that could be used. Typically configurable material is used in Made To Order (MTO) environment. However frequently ordered configurations may be planned with a material variant which needs to have a material master record.

Thus Material variants may have stock and value. Depending upon characteristic values chosen at sales order entry Sales Order BOM is created. Routing operations are also chosen depending upon which BOM components are assigned to them.


Q: Will Source List automatically appear in Material Master as default if maintained at plant level using OME5?

A: If you have maintained source list requirement in OME5 and have not maintained the source list for the material. PO cannot be released. You are required to maintain source list for all materials in the plant where the indicator is set if you maintain source list at plant level. Else you can make use of info record to do so automatically.


Q: We have One company with a plant and another company with a sales organization. Which is better option between these - PO or Stock Transfer Order ?


A: 1) Cross company Stock Transport Orders can be done.

2) Configure using transaction OMGN.

3) Depending upon the sending and receiving plants, maintain sales organization and customer data in customizing.

4) Maintain the supplying plant as a vendor and attach the plant to the vendor in the Vendor Master.

5) Material type has to be HALB or HAWA.

6) Ensure that the company with sales Organization has a plant to take care of stocking.

7) The PO used is NB and not Stock Transfer PO.

8) Configure SD for inter-company billing to enable picking up the pricing procedure for billing.

9) Carry Out delivery through process delivery due list and billing through process billing due list.

Q: We can make field mandatory. We want to make a default value to a Particular field in the Material Master. Say, We want that the period indicator in the MRP2 view as "P". What is the best way?


A: Use transaction variant. Transaction SHD0 and then Transaction SE93.


SAP Workflow


Q: The following is set up for workflow:


1. Workflow organization Structure with two positions is created and assigned a person to both positions

2. Assign tasks to agent

TS 00007986 Requisition release - TO JOBS

TS 00008014 Purchase requisition release refused - GENERAL

TS 00008018 Requisition released - GENERAL

TS 00008348 Requisition release reset - GENERAL

WS 00000038 Workflow for purchase requisition release - TO JOBS

3. Activate event linkage

WS 00000038 Workflow for purchase requisition release
WE BUS2009 RELEASESTEPCREATE Purchase requisition Release step create is activated.

4.Activated release codes for workflow
[1= Role resolution with group, code, and plant (T16FW)]


5. Assigned release codes to agent (JOBS created in 1)

The following error appears
"Work item 60772: Linkage to object BUS2009 event REJECTED cannot be written ".

A: Use transaction SWE2. Make sure "object BUS2009 event REJECTED" is enabled.